Schöck Isokorb® XT/T type K-ID opens up new perspectives for the installation of balconies. With this system, precast balconies or canopies can be subsequently anchored to the new building. This means more flexible construction process and production in the precast plant. Slab concreting and balcony anchoring times are now independent of each other. This is a benefit in cost and time for planners, contractors and the precast industry. Schöck Isokorb® XT/T type K-ID is an innovative solution for the thermal separation of retrofit balcony extensions, based on the dependable Schöck Isokorb® technology that has been established for years.

read more
BIL_NEWS_Isokorb-ID_16z9_FHD_21RL

Innovation with proven Schöck Isokorb® technology

  • Independent installation time of the prefabricated balcony in new buildings
  • Optimisation of the construction process through subsequent balcony installation
  • Reduction of construction cost
  • Flexible production planning and capacity utilisation
  • Minimisation of the risk of damage and pollution
  • Reduction of scaffolding costs
  • Time-saving: balcony completely self-supporting and load-bearing after 48 hours
Installation
BIL_IK_EB_DET_Einbaudetail-IDock-Step-1_#SALL_#AOF_#V1.jpg

Preparing reinforcement

Install the Schöck IDock® slab element in the on-site reinforcement. The Schöck IDock® edge element ensures exact positioning in the formwork.

BIL_IK_EB_DET_Einbaudetail-IDock-Step-2_#SALL_#AOF_#V1.jpg

Concreting the slab

Pour the concrete and wait for it to harden. Remove the recesses of the slab element and the edge element before installing the balcony.

BIL_IK_EB_DET_Einbaudetail-IDock-Step-3_#SALL_#AOF_#V1.jpg

Inserting the precast balcony

Place the Schöck Isokorb® ID of the precast balcony in the openings provided. The optimal time for this step is after the structural work and before installing the windows.

BIL_IK_EB_DET_Einbaudetail-IDock-Step-4_#SALL_#AOF_#V1.jpg

Pouring and hardening of concrete

Fill the recesses in the slab with freshly poured concrete. Within 48 hours, the concrete has hardened, and the balcony has its full load-lbearing capacity.